Free ISTQB Advanced Level – Test Manager Quiz

Home > Free Quizzes > Free ISTQB Advanced Level – Test Manager Quiz

Free ISTQB Advanced Level – Test Manager Quiz

ISTQB - Test Manager Quiz

 

Question 1 of 5

(1)
Which of the three [3] statements are correct about risk based testing?


Question 1 of 5

Question 2 of 5

(2)
ABC is a software company based in USA that builds software to the retail community. Software is tested by two testing teams located in India and China. Testers do not work for ABC company. However, they have very good communication between the project team and well defined expectations for the quality of the software.

What type of test effort is described above?

Question 2 of 5

Question 3 of 5

(3)
IEEE 10440-1993 specifies a standard for defect reporting.
Which of the following attributes should be in a defect report as per ISTQB Syllabus?
 

Question 3 of 5

Question 4 of 5

(4)
Select the correct statement;

I. Comparing actual progress against the plan is part of Test Controlling activity.
II. Updating the test plan if needed is part of test controlling activity.
III. Prioritization criteria identified during risk analysis should be applied only during test execution.
IV. Test conditions are identified by analyzing the test basis and test objectives.

Question 4 of 5

Question 5 of 5

(5)

Test team created 250 test cases to be executed for a project where test execution cycle length is 25 days. At the end of day 12 of testing, team completed execution of 80 test cases and did not find any defects.

Based on these data, what is the current testing progress (select the best two [2] choices)?

Question 5 of 5